Data Center Power ...
The building is supplied with triple power feeds
from the utility company. In the event of a power outage, the data center
is equipped with a 1500 KVA ONAN diesel generator. The generator is
tested every week. When a power outage is detected, the generator will
start automatically within 15 seconds. With one tank of gas in the
generator, it can power 15000 servers for 36 hours.
Fuel can be added to keep the network up and running indefinitely.
|
The data center also uses an MGE data center Uninterruptible Power Supply (UPS).
This UPS has been installed to constantly monitor and regulate the quality of
power coming from the wall so that equipment always receives the clean 120-volt
power. |